INSTALLATION
- Dig landscape
trench 1" (25mm) deeper than the edging being set.
- For straight
runs, the installer may want to run a string to serve
as a guide.
- Set the edging
into the landscape trench with the top 1/2" (12.5cm)
above what will become the compact finish grade.
- The installer
may want to install the entire straight run using stakes
that are half driven in to "tack" the PermaStrip
in place. This will allow the installer when standing
back and viewing the installation to make minor adjustments
to achieve a perfectly straight run.
- Start at the
beginning of the bed area and drive the stakes into their
locked position. (Diagram A)
- Connections
are made using the 4" Sliding Connector. (Diagram
B)
Note: When using a Weed Fabric under stone be sure to
lap the fabric up the face of the PermaStrip. The weight
of the stone will pull the fabric partially down PermaStrip
leaving you sufficient coverage.
- At the end
of the bed area, cut the section to the desired length
and stake down. Begin your next bed area with the remaining
portion of the cut section.
- Forming Angles:
"V-notch" and/or cut the bottom of the edging
halfway up using a hacksaw. Bend up to the desired angle
using a hammer to stiffen angle. This forms a 1/2"
radius on top avoiding sharp corners.
NOTE: When installing Aluminum edging
in direct contact with ACQ treated lumber we recommend installing
a barrier material such as Grace Vycor® Deck Protector™.
If
you have any additional questions, please contact us at
1.800.356.9660 or email
us. |